Dismantling of production units and areas within operating refineries, as well as dismantling and demolition of entire refineries. In addition, Lezama has worked on the design, commissioning and operation of a low-temperature thermal desorption plant for hydrocarbon-contaminated sludge at the Petronor refinery in Bizkaia.

FEATURED PROJECTS

DISMANTLING OF PDL UNIT AND TANKS

    Facility: Dismantling of the former Cepsa PDL unit at the Gran Bilbao facilities, initiating urban development in the region.

    Client: CEPSA

    Duration: 12 months

    Location: Barakaldo, Bizkaia

    Area: 50.000 m2

    DECOMMISSIONING OF TANKS AND THERMAL DESORPTION PLANT

    Facility: Demolition of the tanks at the Petronor refinery in Bizkaia, as well as the remediation of the soils in its basins through the operation of a low-temperature thermal desorption plant.

    Client: PETRONOR

    Duration: 6 months

    Location: Muskiz, Bizkaia

    Area: 75.000 m2

    DISMANTLING OF HYDROCARBON TANKS

    Facility: Dismantling of tanks and auxiliary installations of a hydrocarbon logistics plant at sea level.

    Client: CLH

    Duration: 3 months

    Location: Mahón, Menorca

    Area: 750 m2

    DECOMMISSIONING OF COGENERATION PLANT AND ANCILLARY FACILITIES

    Facility: Cogeneration plant at the Ercros chemical production facility.

    Client: Ercros

    Duration: 4 months

    Location: Tarragona, Cataluña

    Area: 6.000 m2

    DEMOLITION OF THERMAL POWER PLANT - PUERTOLLANO REFINERY REPSOL

    Facility: Demolition of the refinery’s old thermal power plant and the reactor house of the auxiliary building.

    Client: Repsol Química

    Duration: 9 months

    Location: Puertollano, Castilla – La Mancha

    Area: 18.500 m2